Oracle urges FERC to expedite New Mexico gas pipeline for Project Jupiter

· By PetrFlux Newsroom · Source: BN-Pipeline
Image: original source (BN-Pipeline), used for reference with attribution.

Oracle Corporation (NYSE:ORCL) has renewed its push for federal regulators to expedite approval of a crucial natural gas pipeline, warning that regulatory friction threatens to delay the startup of ...

Skip to navigation Skip to main content Skip to right column Yahoo Finance Sign in U.S.

markets open in 2h 18m US Markets US Markets Europe Markets Asia Markets Cryptocurrencies Rates Commodities Currencies U.S.

markets open in 2h 18m S&P Futures 7,864.75 +9.00 +0.11% Dow Futures 52,068.00 +133.00 +0.26% Nasdaq Futures 30,719.00 -72.50 -0.24% Russell 2000 Futures 2,805.30 +5.20 +0.19% 10-Yr Bond 5.22 -0.02 -0.44% VIX 15.33 +0.06 +0.39% Gold 4,158.50 -18.80 -0.45% Bitcoin USD 83,333.94 +83.87 +0.10% Crude Oil Nov 26 95.49 +1.35 +1.43% US Private Equity 10,967.34 -1.52 -0.01% ADVERTISEMENT Oracle urges FERC to expedite New Mexico gas pipeline for Project Jupiter Luke Juricic Tue, October 13, 2026 at 2:52 PM PDT 2 min read ORCL +4.23% BE +0.45% Investing.com -- Oracle Corporation (NYSE:ORCL) has renewed its push for federal regulators to expedite approval of a crucial natural gas pipeline, warning that regulatory friction threatens to delay the startup of its massive Project Jupiter data center campus in New Mexico.

The software giant urged the Federal Energy Regulatory Commission to grant swift authorization for the 17.8-mile Green Chile pipeline, which is designed to transport approximately 400 million cubic feet of natural gas daily to power the facility's microgrid infrastructure.

Before you buy NVIDIA: our AI model's stock picks are beating the market by 120%+.

See the list now » The project relies on fuel cell technology from Bloom Energy to generate off-grid electricity, avoiding strain on the regional transmission system.

However, the pipeline's operational timeline has already slipped to February 2027, well past its initial August target, after opposition from local officials forced developer Transwestern Pipeline Co., a subsidiary of Energy Transfer LP, to reroute the line away from state lands onto federal territory.

Against that backdrop, regulatory hurdles continue to accumulate despite federal environmental assessments progressing through standard comment periods.

Environmental advocacy groups and New Mexico Attorney General Raúl Torrez have pushed FERC to broaden its environmental review, demanding the agency evaluate the combined footprint of both the data center and the pipeline before granting final clearance.

Our AI's list of investor-grade stock picks for October just dropped » To mitigate operational delays during the prolonged approval process, Oracle has considered utilizing trucked natural gas supplies to initiate early commissioning work at the site, Bloomberg reported previously.

While trucking offers a temporary stopgap, a strategy the company has previously deployed on smaller deployments in Utah and Texas, it remains insufficient to supply the immense energy demands required for full-scale data center operations.

For Oracle, the stakes extend beyond project timelines to encompass substantial regional economic commitments tied to the four-building campus.

Original source: BN-Pipeline — PetrFlux publishes verified summaries only, and always links back to the original report. See our editorial policy.