Nexans starts manufacturing 525 kV subsea cables for LanWin2 offshore wind grid connection

· By PetrFlux Newsroom · Source: Offshore Energy
Image: original source (Offshore Energy), used for reference with attribution.

Nexans has started the production of 525 kV high-voltage direct current (HVDC) subsea cables for the LanWin2 offshore grid connection in Germany....

1 minutes read LinkedIn X Email Nexans Nexans has started the production of 525 kV high-voltage direct current (HVDC) subsea cables for the LanWin2 offshore grid connection in Germany.

The France-based cable manufacturer says this marks the first industrial-scale production of its 525 kV HVDC cross-linked polyethylene (XLPE) subsea technology.

Production is taking place at Nexans’ facility in Halden, Norway.

Nexans secured the approximately €1 billion contract for LanWin2 in January 2025 under a framework agreement signed with TenneT in 2023.

The contract covers the engineering, procurement, construction and installation of around 250 kilometers of 525 kV HVDC onshore and offshore export cable systems.

The start of production follows the qualification of Nexans’ 525 kV HVDC XLPE subsea technology, moving the project from technology qualification into full-scale manufacturing and delivery, according to the company.

LanWin2, the 2 GW grid connection designed to transmit offshore wind power from the German North Sea to the Heide region in Schleswig-Holstein, also includes an offshore converter platform being delivered by the Siemens Energy and Dragados Offshore consortium.

First steel was cut for the platform in September 2025.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

Daily Offshore Energy News in Your Mailbox Join thousands of industry professionals who start their day with our newsletter.

Trending Now 1 Methanol-ready energy subsea construction vessel arrives in Norway for completion 2 Equinor employs 2009-built Odfjell Drilling rig for additional wells 3 Nexans starts manufacturing 525 kV subsea cables for LanWin2 offshore wind grid connection 4 More oil found at permit offshore Gabon Daily Offshore Energy News in Your Mailbox Join thousands of industry professionals who start their day with our newsletter.

Original source: Offshore Energy — PetrFlux publishes verified summaries only, and always links back to the original report. See our editorial policy.

Related News

More Power Generation news →